Current and Upcoming Projects

SW 18th Street Resurfacing


This project will involve the resurfacing of SW 18th Street between Dixie Highway and the El Rio Canal Bridge (approximately 1400 feet west of Dixie Highway).  Construction is tentatively scheduled to begin early March 2018 and will extend for a duration of 210 working days, with a tentative completion date around October 2018.  Vehicles will be able to travel east and westbound along SW 18th Street during this time, however, SW 18th Street may be reduced to one (1) travel lane periodically to allow for the work to be completed.
Expected Start Date:
March 12, 2018
Expected Completion Date:
October 2018 (approximately 210 days)
More Information:
City of Boca Raton Engineering Division, 561-416-3401

Camino Real Intracoastal Waterway Bridge


The Camino Real Intracoastal Waterway Bridge project, overseen by Palm Beach County Roads & Bridges, will result in a complete renovation of the existing Camino Real bridge.  The renovation will require the complete closure of the Camino Real bridge to vehicles and pedestrians for a period lasting approximately 12 months.
Start Date:
April 12, 2018
Expected Completion Date:
Approximately April 12, 2019 (approximately 12 months after start date)
More Information:
Barry Meave, Palm Beach County Roads & Bridges, 561-233-3976

I-95 Express Lanes


The Florida Department of Transportation (FDOT) is implementing Phase 3B-1 of the I-95 Express Lane project, continuing express lanes constructed and currently under construction in Miami-Dade and Broward Counties north toward Glades Road. The purpose of the 95 Express Lanes is to improve mobility, relieve congestion, provide additional travel options, enhance transit services, accommodate future growth and development in the region, enhance emergency evacuation, and improve system connectivity between key limited access facilities in South Florida.
Expected Start Date:
2018
Expected Completion Date:
August 2021
Estimated Construction Cost:
$102 million
Project Website:
http://www.d4fdot.com/bcfdot/95_express_phase_3b1.asp
More Information:
Andi Pacini, FDOT PIO, [email protected] or 954-299-6561

Spanish River Boulevard Intracoastal Waterway Bridge


The Spanish River Intracoastal Waterway Bridge Project, overseen by the Florida Department of Transportation (FDOT), will result in routine maintenance for the existing Spanish River Boulevard Bridge.  The maintenance will require closures at the Spanish River Bridge to vehicles and pedestrians for a period lasting approximately 3 months.
Expected Start Date:
May 2019
Expected Completion Date:
July/September 2019

Palmetto Park Road El Rio Canal Bridge


The Palmetto Park Road El Rio Canal Bridge Project, overseen by Palm Beach County Roads and Bridges, will result in a complete widening of the existing Palmetto Park El Rio Canal Bridge.  The project will require closures at the Palmetto Park El Rio Bridge to vehicles and pedestrians for a period lasting approximately 9 months.
Expected Start Date:
September 2019
Expected Completion Date:
June/July 2019
More Information:
Palm Beach County Roads and Bridges, 561-233-3950

Palmetto Park Road Intracoastal Waterway Bridge


The Palmetto Park Road Intracoastal Waterway Bridge Project, overseen by Palm Beach County Roads and Bridges, will result in routine maintenance for the existing Palmetto Park Road Intracoastal Waterway Bridge.  The maintenance will require closures at the Palmetto Park Road Bridge to vehicles and pedestrians for a period lasting approximately 4 months.
Expected Start Date:
October 2020
Expected Completion Date:
January/February 2021
More Information:
Palm Beach County Roads and Bridges, 561-233-3950