This project will involve the resurfacing of SW 18th Street between Dixie Highway and the El Rio Canal Bridge (approximately 1400 feet west of Dixie Highway). Construction is tentatively scheduled to begin on March 12, 2018 and will extend for a duration of 210 working days, with a tentative completion date around October 2018. Vehicles will be able to travel east and westbound along SW 18th Street during this time, however, SW 18th Street may be reduced to one (1) travel lane periodically to allow for the work to be completed.