[ARCHIVED] City Projects Update

Construction worker waving while milling street


Paving Projects Update

To maximize the appearance and integrity of the roads, the City’s Engineering Division has been making their way through the City completing pavement resurfacing projects. By using a uniform methodology to assess pavement conditions, periodic inspections and a predictive model to optimize timing of roadway resurfacing, the following neighborhood projects have been completed or are underway. As part of the City’s Capital Improvement Program (CIP), the 6.4 million dollar resurfacing projects are on track to be completed by late summer 2018.

  • SW 18th street between Dixie Highway and the El Rio Canal – In Progress – Estimated completion October 2018
  • Por La Mar - Complete
  • The Estates Section – Complete
  • St. Andrews Blvd from Glades to Palmetto Park Road – Complete
  • SW 12th Avenue between Camino Real and 18th Street - Complete
  • Blue Inlet - In progress - Complete
  • Harbor East Estates - Complete
  • Villa Rica - Complete
  • Knob Hill - Complete
  • Cedar Ridge - Complete
  • Vista Hills - Complete
  • Sunset Ridge - Complete


Facebook Twitter Email

Other News in Current Affairs & Topics

Sustainability Survey

Take the Sustainability Survey!

Posted on: October 6, 2023
2023 Boca Raton Bowl

It's Game Time in Boca Raton

Posted on: December 4, 2023
Deck the House

NEW! Holiday Decorating Contest

Posted on: November 1, 2023
Construction Updates

Gumbo Limbo Nature Center Construction

Posted on: December 1, 2023
2023 Boca Jolly Days

Celebrating Holidays in Boca

Posted on: November 13, 2023
Golf Newsletter - November 2023

Golfing in Boca Raton

Posted on: November 7, 2023